The timelines which you provide while creating an engagement will be applied to all the assessments which are a part of that engagement. It is possible to update the timelines for individual assessments after an engagement is created. The following are the instructions to add unique timelines for individual assessments.

  • Navigate to the 'Engagements' page.

    mceclip0.png

  • Select the engagement to which the assessment in question belongs to.
  • Click on the 'Actions' option for the assessment whose timelines need to be updated.
  • Click on 'Edit Timelines'

    mceclip1.png

  • Choose the appropriate 'State date' and 'End date'.

    mceclip2.png

  • Click on 'Update' and the timelines for the selected assessment will get updated.